Salbouk and Buwayb Water Plant
Scope of work: Supply, installation & commissioning services for a new cooling tower for the National water company with a capacity of 400 M3/HR@4NOS. The project scope also included the demolition of existing cooling tower, concrete basin, piping network and electrical items.
Dar Al Riyadh was also responsible for the civil works for the cooling tower basin construction and installation of 120 M SS 12″ piping and 60 M DI 24″ required valves. We also supplied and installed the PLC based operation and control panel for fan motor. The scope also included supplying and installing all required instruments and cables for the fan motor.
Scope
- Specification, Installation and Commissioning
- Industrial Systems & Solutions
Client
- National Water Company (NWC)